21 de octubre de 2026 · Ordinance · 2026-333
Approve the findings to authorize exemption to the competitive bidding requirements and authorize competitive solicitation for the use of the alternative contracting method of a Construction Manager/General Contractor for the Montgomery Park Streetcar Extension Project
Abrir el original en portland.gov ↗
Resumen en lenguaje sencillo
City picks a different way to hire builder for NW streetcar extension
This lets the city skip the usual rule of hiring the lowest bidder to build the Montgomery Park Streetcar Extension. Instead, the city will ask companies for proposals and choose a Construction Manager/General Contractor, a builder who helps during design and then builds the project. The streetcar would run along NW 23rd Avenue north of NW Northrup Street to new one-way routes on NW Roosevelt and NW Wilson streets.
Decision: Moved forward to a second reading, a required second council vote. No vote count was given.
Who it affects: People who live, work or travel in Northwest Portland near NW 23rd Avenue and Montgomery Park.
Money: The builder contract is estimated at $63 million to $73 million. The whole project is estimated at $195 million, including up to 12 new streetcars, with about 50-60% expected from a federal grant. No new money is requested in this ordinance.
Next: Second reading on October 21, 2026 at 6:00 pm. Construction is expected to begin in the 2029-30 budget year.
Official record
Escrito por IA a partir del registro oficial y revisado por una persona. 14 de octubre de 2026
Resumen en lenguaje sencillo
City picks a different way to hire builders for streetcar extension
This lets the city skip the usual rule of hiring the lowest bidder to build the Montgomery Park Streetcar Extension. Instead, the city will ask builders for proposals and pick one to help during design and then build the project. This hiring method is called Construction Manager/General Contractor. The extension will carry the streetcar north on NW 23rd Avenue to new one-way tracks on NW Roosevelt and NW Wilson streets.
Decision: Passed, 12 to 0.
Who it affects: People who live, work or travel in Northwest Portland near NW 23rd Avenue and Montgomery Park.
Money: The builder's contract is estimated at $63 million to $73 million. The whole project is estimated at $195 million, including up to 12 new streetcars, with a federal grant expected to pay 50% to 60%. The city says these are early, low-confidence estimates. No new money was requested in this vote.
Next: Design and environmental review happen in 2026 and 2027, with more community outreach. Construction is expected to start in the 2029-30 budget year.
Official record
Escrito por IA a partir del registro oficial y revisado por una persona. 21 de octubre de 2026
- Full title
- Approve the findings to authorize exemption to the competitive bidding requirements and authorize competitive solicitation for the use of the alternative contracting method of a Construction Manager/General Contractor for the Montgomery Park Streetcar Extension Project
- Status
- Passed
- Document number
- 2026-333
- Introduced by
- Mayor Keith Wilson
- City department
- Transportation
- Requested council date
- October 21, 2026
- Purpose and background
- The purpose of this council ordinance is to approve an alternative contracting method for the construction phase of the project, called Construction Manager / General Contractor (CM/GC). Council approval is required to approve an alternative to the typical low-bid method of construction contracting. Based on the Findings herein, use of a CM/GC would support successful completion of the MPSE project in an efficient manner to achieve PBOT and partner goals for the area. General project background: The Montgomery Park Streetcar Extension project (MPSE) will extend the existing Portland Streetcar North-South (NS) line along NW 23rd Avenue north of NW Northrup Street to a new parallel one-way couplet along NW Roosevelt and NW Wilson streets. The project includes multimodal extensions of NW Roosevelt Street, NW Wilson Street, and NW 25th Avenue in the couplet area. This project will also rehabilitate NW 23rd Avenue between NW Vaughn and NW Lovejoy streets, including accessibility and stormwater upgrades.
- Financial and budgetary impacts
- The total project cost is $195M (low confidence estimate), which includes the cost of purchasing up to 12 new streetcar vehicles. The project is primarily funded by the Federal Transit Authority's Small Starts Capital Investment Grant program (estimated to provide 50-60% of the project's total funding). Additional funding sources include Portland Streetcar Reserve funds, Northwest Parking Stakeholder Advisory Committee funds, Portland Clean Energy Fund, a Local Improvement District, Regional Flexible Bond Funds via Metro, and Transportation System Development Charges. Costs for this project will be posted to PBOT Capital Project T01304, and is included in PBOT's FYs 2026/2027, 2027/2028, and 2028/2029 for design and environmental clearance, with construction anticipated to begin in FY 2029/2030 – the project is included in the five-year CIP forecast. The CM/GC contract is estimated at $63-73M, based on work performed by an engineering consultant team and evaluated by City of Portland professional staff. There is no additional funding requested as part of this ordinance.
- Economic and real estate impacts
- This ordinance authorizes an exemption from low-bid procurement to allow use of a Construction Manager/General Contractor (CM/GC) delivery method. The ordinance itself does not directly impact economic activity or real estate development. However, it supports efficient delivery of the broader Montgomery Park Streetcar Extension project, which is intended to improve transit access to a historically industrial area and may facilitate future redevelopment opportunities. Any such impacts would result from the project as a whole rather than this procurement decision.
- Community impacts and community involvement
- While developing the Locally Preferred Alternative for the Montgomery Park Streetcar Extension as part of the Montgomery Park Area Plan process between 2019 and 2024, the City did extensive community outreach in Northwest Portland to help shape project outcomes, including: 7 meetings of a Project Working Group representing various community and business viewpoints 2 online Open Houses Outreach through 2 community-based organizations in the area Meetings and presentations with neighborhood groups, advocacy groups, and business associations Postcards sent to 7,000 area addresses, in both English and Spanish (with additional translations available upon request) Canvassing to businesses along the proposed alignment 179 respondents to an online survey Intercept surveys near regulated affordable housing and existing transit stations near the proposed alignment Tabling at events in Northwest Portland Phone calls, emails, and conversations with interested community members Feedback on Discussion Draft elements of the Montgomery Park Area Plan, and testimony on the Proposed Draft of the plan Overall feedback was supportive of the project, with concerns around project funding mechanisms, loss of industrial jobs, and potential indirect displacement as part of changing market dynamics resulting from public investment. To address these concerns, the City has worked to minimize local funding source or local contribution funding needs, and included affordable housing and middle-wage job target requirements as part of a related Public Benefits Agreement adopted as part of the Montgomery Park Area Plan and signed by the large-share area property owner, 1535 LLC. As the project advances design and conducts environmental review during 2026 and 2027, engagement will continue in the area.
- 100% renewable goal
- Portland Streetcar is 100% electricity powered and has been shown to increase transit trips powered by renewable energy where available The Montgomery Park Streetcar Extension project's cars will run off-wire, meaning they will be powered by on-board batteries for the footprint of the new project area Batteries will be charged along the current streetcar alignment while traveling the route