Bond Program Update
September 15, 2026
Agenda
2
● Program Status
● Schedule
● Program Budgets
● Project Updates
Program Status Update
3
2012 Bond Program Project Status
Total Projects Pre-Planning Design Phase Construction Post Construction Completed
34 1 1 1 1 31
4
NOTE: source data: Ebuilder
reports by bond measure,
sorted by project status.
Audit of Project Completion and
Closeout statuses is currently
ongoing.
2017 Bond Program Project Status
Total Projects Pre-Planning Design Phase Construction Post Construction Completed
191 4 7 16 53 111
5
NOTE: source data: Ebuilder
reports by bond measure,
sorted by project status.
Audit of Project Completion and
Closeout statuses is currently
ongoing.
Total Projects Pre-Planning Design Phase Construction Post Construction Completed
116* 4 5 30 32 45
2020 Bond Program Project Status
6
*Approximately $512 M
remaining to be scheduled for
2020 Bond.
NOTE: source data: Ebuilder
reports by bond measure,
sorted by project status.
Audit of Project Completion and
Closeout statuses is currently
ongoing.
2025 Bond Program Project Status
* Total projects will increase as
the program progresses.
7
Total Projects Pre-Planning Design Phase Construction Post Construction Completed
27* 16 5 1 5 0
Schedule and Budget Update
8
Program Schedule Update
9
Design Phase Procurement Land Use Permitting Construction
Phase Closeout
Program Schedule September 2026 2026 2027 2028 2029 2030
Jefferson High School
Cleveland High School
Ida B. Wells High School
Grice-Adair Center for Educational Excellence
All future dates, durations and projections are subject to change
20302025 2026 2027 2028 2029
JHS Overall Project Schedule
BUILDING PERMITS
LAND USE
BUILDING
CONSTRUCTION
COST
STUDY
PROJECT REDESIGN &
CONSTRUCTION DOCUMENTS
SPRING 2027
BASEBALL FIELD
SOFTBALL FIELD
S PARKING LOT
COMPLETE
TRACK & FIELD
GRANDSTANDS
TENNIS COURTS
N PARKING LOT
COMPLETE
FALL 2030
PROJECT
COMPLETE
NEW BUILDING CONSTRUCTION
SOUTH FIELDS
CONSTRUCTION
SPRING 2027
START NEW
BUILDING
CONSTRUCTION
DEMO BUILDING
AND COMPLETE
SITEWORK
SUMMER 2029
JEFFERSON HS
COMPLETE
MOVE
IN
MAY 2026
GROUNDBREAKING
20302025 2026 2027 2028 2029
CHS Overall Project Schedule
LAND USE
MOVE
IN
COST
STUDY
PROJECT REDESIGN &
CONSTRUCTION DOCUMENTS
FALL 2028
CHS STADIUM OPENS
SUMMER 2029
NEW CLEVELAND HS
COMPLETE
SUMMER 2028
MOVE INTO IMPROVED
STADIUM
JULY 2026
CHS MOVES TO MARSHALL
DEMO & EARTHWORK
START
SUMMER 2029
MOVE INTO
NEW BUILDING
BUILDING
PERMITS
BUILDING CONSTRUCTION
JUNE 2026
GROUNDBREAKING
DEMO
20302025 2026 2027 2028 2029
IBW Overall Project Schedule
LAND USE
BUILDING CONSTRUCTION
DEMO BUILDING
AND COMPLETE
SITEWORK
MOVE
IN
COST
STUDY
PROJECT REDESIGN &
CONSTRUCTION DOCUMENTS
AUGUST 2029
NEW IDA B WELLS HS
COMPLETE
AUGUST 2030
FIELDS AND
SITEWORK
COMPLETE
SPRING/SUMMER 2029
NEW BUILDING
COMPLETE
WINTER 2026/2027
START BUILDING
CONSTRUCTION
FALL 2030
PROJECT
COMPLETE
BUILDING
PERMITS
2012 Program Financial Status 7/1/2026
Modernizations: Franklin HS, Grant HS, Roosevelt HS, and Faubion PK-8
Middle School Science Upgrades
Consolidated Projects: Accessibility, Seismic
Project Budget
Outstanding
Encumbrance Amount Paid to Date Remaining Balance
Franklin HS Mod $110,950,414 $0 $110,950,414 $0
Grant HS Mod $155,300,188 $0 $155,300,188 $0
Roosevelt HS Mod $97,128,043 $0 $97,128,043 $0
Faubion Replace $30,653,663 $0 $30,653,663 $0
Grant Upper Field $3,170,988 $0 $3,170,988 $0
RHS Phase IV $6,153,741 $0 $6,153,741 $0
Other Projects $112,740,428 $8,100 $112,710,428 $21,900
Grant & Franklin Add Ons $367,663 $92,107 $75,464 $200,092
Administration $31,284,018 $0 $31,284,018 $0
Contingency $83,104 $0 -$902 $84,006
PPS 2012 Bond Program Total $547,832,249 $100,207 $547,426,043 $305,998
Current balance of $242k as
of 9/1/26
2017 Program Financial Status 7/1/2026
Modernizations: Benson Polytechnic, Lincoln, McDaniel, Kellogg Middle School and Multiple Pathways to
Graduation
Consolidated Projects: Water Quality, Security Upgrades, New Roofs, Asbestos Abatement, Radon Remediation,
Lead Paint Stabilization, Life Safety Upgrades, Accessibility, Seismic
Project Budget
Outstanding
Encumbrance Amount Paid to Date Remaining balance
Benson HS Mod $146,614,560 $378,357 $143,715,501 $2,520,702
Benson Add Ons $2,865,020 $232,666 $1,266,243 $1,366,111
Benson Swings $12,199,595 $0 $12,199,595 $0
Lincoln HS Repl $240,836,448 $28,738 $224,096,580 $16,711,130
Kellogg MS Replace $57,648,703 $0 $57,648,703 $0
McDaniel Mod $197,000,000 $48,407 $196,817,745 $133,848
Health & Safety $168,865,686 $22,536,517 $124,615,088 $21,714,081
Athletics $4,734,678 $174,034 $2,278,729 $2,281,914
Administration $61,087,401 $168,934 $60,908,060 $10,408
Contingency $593,194 $0 $0 $593,194
PPS 2017 Bond Program Total $892,445,285 $23,567,653 $823,546,245 $45,331,387
2020 Program Financial Status 7/1/2026
Modernizations: Jefferson HS, Pre-Planning/Design Ida B Wells and Cleveland HS, The Center of Black
Excellence, Roosevelt (added capacity), and Benson
Consolidated Projects: Curriculum Materials, New Technology for classroom and distance learning, Health &
Safety, Seismic, Security, Re-Roofing
Project
Budget
Managed by
PROCEDEO
Budget Managed
by PPS
Outstanding
Encumbrance
Amount Paid to
Date Remaining Balance
Benson 2020 Funds $164,903,890 $640,328 $162,803,433 $1,460,129
Jefferson HS Mod $366,007,500 $38,429,302 $30,053,013 $297,525,185
Jefferson Add Ons $152,175 $149,945 $250 $1,980
CEE $60,000,000 $34,238 $16,222,680 $43,743,082
Cleveland HS – Design $23,679,515 $8,412,380 $15,270,600 -$3,465
Cleveland Swing Site $137,500 $1,800 $105,905 $29,795
Wells HS – Design $20,000,000 $2,404,163 $17,584,080 $11,757
Roosevelt PhV – Design $2,000,000 $1,035 $97,625 $1,901,340
MPG Building $80,447,075 $267,192 $77,947,593 $2,232,290
Curriculum $63,319,191 $1,255,550 $54,617,744 $7,445,897
Technology $136,100,000 $16,660,493 $91,534,529 $27,904,978
Infra Projects $268,153,105 $19,787,893 $235,023,435 $13,341,777
Administration $51,706,045 $1,239,513 $34,440,015 $16,026,517
2017 Bond Balance $0 $0 $0 $0
Contingency – OSM $79,451,387 $0 $0 $79,451,387
Unallocated Funds $17,649,899 $0 $0 $17,649,899
PPS 2020 Bond Program Total $469,976,690 $863,730,592 $89,283,832 $735,700,902 $508,722,548
2025 Program Financial Status 7/1/2026
Modernizations: Cleveland HS, Ida B Wells HS, and Jefferson
Consolidated Projects: Security Upgrades, Seismic, Technology, Improvements for Roosevelt, Lincoln,
Franklin, and Grant, and New Athletic Hub Facilities at Jackson MS and Marshall Campuses
Project
Budget Managed
by PROCEDEO
Budget Managed
by PPS
Outstanding
Encumbrance
Amount Paid to
Date Remaining Balance
Priority Scope $190,000,000 $10,622,793 $344,233 $179,032,974
Athletics $79,000,000 $1,347,024 $2,047,435 $75,605,541
Technology $176,000,000 $3,916,460 $26,452,579 $145,630,961
Physical Education $10,000,000 $0 $0 $10,000,000
Curriculum $56,000,000 $0 $0 $56,000,000
Jefferson HS Modernization $100,000,000 $0 $0 $100,000,000
Cleveland HS Modernization $448,911,745 $12,273,030 $393,615 $436,245,100
Ida B Wells HS Modernization $429,350,000 $29,359,062 $507,760 $399,483,178
Elementary & Middle Schools $171,738,255 $0 $0 $171,738,255
Admin $83,050,000 $57,898,825 $7,570,008 $17,581,167
Contingency $125,956,806 $0 $0 $125,956,806
PPS 2025 Bond Program Total $978,261,745 $891,745,061 $115,417,194 $37,315,630 $1,717,273,982
Project Updates
18
Project Overview
Current Phase: In Construction
Scope: New Facility
New Facility: 299,485 SF
Construction Start: Spring 2026
Student Move-In: 29-30 School Yr
Tentative Sub Com: Fall 2030
GMP Construction Timeline: TBD
5210 N Kerby Ave, Portland, OR 97217
ConstructionDesign Procurement
Total Budget CMGC GMP
$466,007,500 GMP: $TBD
Project Budget
Project Status
Construction NTP
6/15/26
Project Update
1 50% CD Review Session complete, estimate reconciliation & review are underway
2 Permits issued for for baseball & softball fields, construction is ongoing
3 Project team met with JHS staff to provide overview of current and future on-site
construction phases and allow for questions & answers
General Scope
✔ New all-electric multi-story building
✔ Includes a theater, health center, teen
parent center, and dance studios
✔ Track and field relocated to the site of
the current structure
✔ New softball field and baseball/soccer
multiuse field
19
Design
50% CD Review
Complete
100% 0%
Jefferson HS Modernization
Contractor (CMGC)
Colas Hoffman
Architect
BORA & LEVER
PPS PM
Steve Effros
PPS Zone 2
Michelle DePass
> JHS Field Construction - 8/21/26
2025 Bond Program Status Update
> JHS Field Construction - 8/28/26
2025 Bond Program Status Update
Project Overview
Current Phase: In Construction
Scope: New Facility
New Facility: 297,000 SF
Construction Start: Summer 2026
Student Move-In: 29-30 School Yr
Tentative Sub Com: Summer 2029
GMP Construction Timeline: TBD
3400 SE 26th Ave, Portland, OR 97202
Contractor (CMGC)
Skanska
Architect
Mahlum
PROCEDEO PM
Scott Mears
PPS Zone 6
Stephanie Engelsman
ConstructionDesign Procurement Design
Total Budget CMGC GMP
$472,553,760 GMP: TBD
Project Budget
Project Status
Construction
Marshall Swing Start - 3/30/26
Demo Start - 7/7/26
Project Update
General Scope
✔ 2 new four-story buildings connected
by a skybridge
✔ Dynamic outdoor courtyard
✔ New arts theater, black box theater, 2
gyms, and dance and wrestling
studios
✔ Improvements to track and athletic
fields
22
Permit 2 Set In
Review
100%
Cleveland HS Modernization
2%
1 The Marshall site is complete and students have moved in for the school year
2 Abatement and demo is underway. Salvage of exterior masonry and interior
materials is nearing completion.
3 Building Permit 1 is currently in review with the City
> CHS Bldg Demo - 8/13/26
2025 Bond Program Status Update
Project Overview
Current Phase: In Design
Scope: New Facility
New Facility: 283,867 SF
Construction Start: Winter 2026
Student Move-In: 29-30 School Yr
Tentative Sub Com: Fall 2030
GMP Construction Timeline: TBD
1151 SW Vermont St, Portland, OR 97219
ConstructionDesign Procurement
Total Budget CMGC GMP
$449,350,000 GMP: $TBD
Project Budget
Project Status
Construction NTP
Pending
Project Update
General Scope
✔ New four-story building including
instructional spaces for Career
Technical Education programs
✔ New performing arts, commons, and
outdoor spaces
✔ Full complement of athletic fields and
upgrade of existing fields on the
Rieke side
✔ The existing pool is not in the scope,
but a new pool support building is
included 24
Design
50% CDs In Review
0%100%
Ida B Wells HS Modernization
Contractor (CMGC)
Hoffman Construction
Architect
BORA Architects
PROCEDEO PM
Gabe Asch
PPS Zone 1
Christy Splitt
1 50% CD Review Session started on 8/12/26
2 Land Use approved on 8/28
3 Permitting submitted to the City and is under review
4 Groundbreaking scheduled for November 13th
Project Overview
Current Phase: In Design
Scope: Renovations
Renovations: TBD
Construction Start: TBD
Tentative Sub Com: TBD
GMP Construction Timeline: TBD
1 N. Fremont St, Portland, OR 97227 Total Budget CMGC GMP
$60,000,000 GMP: $TBD
Project Budget
Project Status
SDs in Progress
Project Update
ConstructionDesign Procurement
General Scope
✔ Renovation of buildings into PPS
Managed Community Center,
supporting programs for students of
all ages and families with space for
Study, Connection, Learning, and
Movement
✔ A portion of the upper floors of the
West Building will remain and be
leased to Community Partner
Organizations
✔ Space allocated for PPS and
Community Partner Administration,
as well as Community Gathering and
an Outdoor Courtyard 25
Design
Grice-Adair Center for Educational Excellence
Contractor (CMGC)
TBD
Architect
DLR
PROCEDEO PM
Khalil Rivera
1 Scope to Budget (STB) review session completed on 8/28, A/E approved to begin
work on SDs
2 Initial cost estimate received and is within budget
3 AE site walks and facility assessments have been completed
Seismic/Roofing - 2026
26
Summer 2026 Construction
Roofing with Seismic
● Scheduled for 2026 Fall completion
○ Woodmere
○ Cesar Chavez
○ Marshall
○ Vestal
Seismic Parts
● Scheduled for 2026 Fall completion
○ Vernon
○ Winterhaven
○ Marysville (Ph 3)
YOUR BOND DOLLARS AT
WORK!
2026 SUMMER
CONSTRUCTION:
$29.4M
Seismic/Roofing - 2027 and Beyond
27
Anticipated 2027 Construction Start
Seismic Parts and Partial Roof
● In Design
○ Richmond (DD Phase)
○ Capitol Hill (DD Phase)
Seismic Parts
● In Design
○ Ainsworth (SRGP awarded, DD phase)
○ Kelly (DD phase)
Full Seismic
● Design in progress
○ Beverly Cleary (CD mid-Sept)
Anticipated 2028 and 2029 Construction
Seismic Parts and Partial Roof
● Beach
○ Pre-Design docs due mid-Sept
Full Seismic and roof
● Rose City Park
○ Pre-Design docs due Aug 31st
YOUR BOND DOLLARS AT
WORK!
2026 SUMMER
CONSTRUCTION:
$16M
Facility Improvement Projects
28
Summer 2026 Construction
● Bridger - Mechanical Upgrades
● Buckman - Cafeteria Flooring Abatement and
Replacement
● Buckman - Sidewalk Replacement
● Boise Elliot – Repaint majority of school
● Capitol Hill - Flooring abatement, structural repairs, new
flooring
● George - Boiler Room Roof Beam Replacement
● Jefferson – Stage rigging repairs
● Kelly - Mechanical Upgrades
● Lent - Mechanical Upgrades
● Classroom Technology Upgrades - Gray, Markham, West
Sylvan, Mt. Tabor , Harrison Park, Laurelhurst, Hosford, Buckman,
MLC, Davinci, Chavez, MLK, Roseway Hts, Alameda, Ainsworth,
Sellwood
● Roosevelt – Science Chemical Storage
● Rose City Park - Boiler Retube
● Sabin – Restroom Pipe Replacement
● Sitton – Truss repair/replacement
● Vestal – Built-in cafeteria table replacement
● DDC Controls Upgrades - Alameda, Beach, Chavez,
James John, Brentwood, Roseway Hts, Sellwood, Sitton,
West Sylvan
● Fire Alarm Upgrades - Glencoe, Marshall Campus,
Woodlawn
Athletic Sites
29
Grant Bowl Lighting
● “Flip the Switch” celebration on September 1st
Jackson Athletic Hub
● Phase 1: Track & Field construction began in June and anticipated to be operationally
accessible by Fall 2026
● Phase 2: Multi-Use Field entering Permitting Phase August 2026
○ Multi-Use completion Spring 2027
Powell Park Multi-Use Field, Lighting, and Support Buildings
● Continuing discussions with Parks for use agreement - meeting 9/8
Land Use Application Planning in Progress
● West Sylvan, Franklin, Roosevelt, Grant Seating
Athletic Sites
30
Marshall Athletic Improvements
● Completed:
○ Light Retrofit
○ Track
○ Field
○ Tennis Courts
○ Gym
○ Weight Room
> Grant Flip the Switch - 9/1/26
2025 Bond Program Status Update
> Grant Wins 2-0! - 9/1/26
2025 Bond Program Status Update
Fall 2026 Look Ahead
33
A round of applause to all of the teams who successfully completed large amounts of work
over the summer. Our work does not stop here. We are continuously planning, designing, and
implementing the work of the district.
Modernizations - Continued field work and demolition, finalizing designs and construction
planning.
Facility Improvements - Planning and design for next summer projects, and ongoing facility
improvements that can be done during winter break
Athletics/PE - Continued work on the Jackson hub, and land use planning for other sites
Security - Planning and implementation of smaller projects to enhance school security
Technology - Continue updated technology deployments to classrooms, and the start of the
ERP modernization moving to our new platform
Current PPS Betterment Savings
Recognized within the first 6-month of PROCEDEO Contract
Total Realized Savings: $20,839,680
For Every $1 PPS has invested in PROCEDEO we have returned
$2.25 in identified saving to the bond program
Total PROCEDEO
Fee Paid to Date
Return on Investment Owner Betterment Savings Breakdown
$6.4M Current ROI
225%
Realized/Reallocated Savings
• Reallocation of funds in 2012 Bond into Projects
• Savings recognized by new processes no need
for temporary labor
• FF&E Coordination Repetitive SOW Corrected
• Negotiated Street Closure Fee Cap with ODOT
• Worked with ODOE to document effort for GET
Questions
Thank You