Bond watchdog group says school building projects are on track
A volunteer community committee that watches how Portland Public Schools spends voter-approved bond money gave its regular report. It found the money is being spent only on allowed projects, there is enough to finish the promised work, and the rebuilds of Cleveland, Jefferson and Ida B. Wells high schools and the Grice-Adair Center are on schedule to open in fall 2029. It also noted an ongoing dispute with the contractor that built Benson High School.
Decision: No vote: this was a report to the board.
Who it affects: Students, families, staff and neighbors at Cleveland, Jefferson and Ida B. Wells high schools and the Grice-Adair Center, and taxpayers who pay for the bonds.
Money: Voters have approved $4.6 billion in school bonds since 2012 (2012: $482 million; 2017: $790 million; 2020: $1.206 billion; 2025: $1.8 billion). About 54% has been spent and $2.1 billion remains, mostly from the 2025 bond. The Cleveland High School rebuild budget is $472,553,760, including $15 million for athletic fields at Powell Park.
Next: Cleveland, Jefferson and Ida B. Wells high schools and the Grice-Adair Center are scheduled to open in fall 2029. Design for the three high schools is due to finish by the end of 2026.
Official record
Написано ИИ по официальному документу и проверено автоматически. 6 октября 2026 г.
Полный текст
PROJECT TEAM MANAGEMENT PLAN
rev. 5/7/26
Portland Public Schools
2020 School Building Improvement Bond
Jefferson HS Modernization
Project Team Management Plan
1. PPS Team
Sr Project Manager Steve Effros seffros@pps.net
Director of Construction Drew Schott drschott@pps.net
Deputy Director Angela Caffrey acaffrey@pps.net
Sr Program Director TJ Hopkins thopkins@pps.net
School Principal Drake Shelton dshelton@pps.net
School Planning Principal Allison Adams aadams@pps.net
School FOM Stetson James sjames2@pps.net
A/E Bora/Lever Architects
Contractor Colas Hoffman Construction
2. Executive Summary
The Jefferson High School Modernization project will modernize the historic Jefferson High
School located at 5210 N Kerby Ave, Portland, OR 97217. The existing 14-acre site includes the
original 1909 school building, plus later additions, and a track and fields.
In late 2019, a Conceptual Master Planning Committee that included parents, teachers, students
and community stakeholders worked together to help inform the budget of the Jefferson High School
Modernization project for inclusion on the District’s successful 2020 Bond measure. In 2022, a
Comprehensive Planning Committee, in coordination with extensive community and District
stakeholder engagement, helped develop a Comprehensive Plan for the Jefferson High School
Modernization project that was approved by the Portland Public Schools Board of Education in
December 2022.
The approved Comprehensive Plan was a multi-phase project that included both renovation and
new construction, with students swinging on-site occupying existing buildings. Those initial phased
plan estimates exceeded the budget, prompting a shift to a single-phase approach with off-site
student relocation to preserve the original 1909 building. However, strong community feedback led
the Board of Education to reconsider the plan of relocating students off-site. This led to a project
1 | Page
PROJECT TEAM MANAGEMENT PLAN
rev. 5/7/26
pivot and in December of 2023, the Board approved a new approach in which it kept students on
campus during the construction of a new building on the North end of the site.
Following development of this new building approach through 2024, under guidance of new
District Staff leadership, the Board directed the three high school modernization projects in
December 2024 to develop cost reduction strategies and revise the Comprehensive Plans for these
projects to align with Board Resolution No. 7051 for high-quality, cost-efficient school construction.
With the Board’s approval of the revised Conceptual Design for this project in April 2025, the
Jefferson High School Modernization project proceeded with the start of Schematic Design for this
revised concept.
3. Project Overview
a. Overview of the bond language re: project
In the July 28, 2020 referral to voters approved by PPS Board of Education, proposed health and
safety investments include “2020 Modernizations - transforming the historic Jefferson… into [a]
modernized 21st century [center] of learning.”
b. Description of the project
The current Comprehensive Plan includes a compact, four-story building accommodating 1,700
students, on the existing track and football field at the North side of the site. In the first phase of
construction, students will remain on site in the existing school buildings during the construction of
the new school. Two new multipurpose baseball and softball fields located to the south of the existing
school will be permitted and constructed during the first phase to avoid the complete loss of athletic
fields during construction.
Upon completion of the new school, students will occupy the new facility and the old school
buildings will be demolished. Following demolition of the old school, a second phase of construction
will complete the site work for the modernization project. This work will be scheduled for completion
before demolition of the existing track and field begins.
4. Project Delivery Model
The Construction Manager / General Contractor (“CM/GC”) method was determined to be the
most appropriate for this project. In the Fall of 2022, the Board of Education granted an exemption
from the traditional Design-Bid-Build low-bid procurement process and approved the use of an
Alternative Contracting Method for the construction of Jefferson High School Modernization.
CM/GC is the commonly used alternative contracting method by local governments for large,
complex projects such as major modernizations involving existing buildings and sites like the
Jefferson High School Modernization Project.
Under the CM/GC contracting method:
2 | Page
PROJECT TEAM MANAGEMENT PLAN
rev. 5/7/26
● The contractor is solicited early in the design phase pursuant to a competitive Request for
Proposals (RFP) process wherein selection is based upon evaluation of factors relating to the
experience, expertise, and project approach of the contractor rather than lowest bid.
● The contractor works with the owner and architect to develop the final design with the goals of
improved constructability and value engineering, which results in fewer change orders and the
ability to expedite the construction schedule. Under the standard design/bid/build (low
bid)method, the design is completed before the project is bid and the contractor brought on
board.
● During the design phase, the owner and contractor negotiate and agree on a guaranteed
maximum price ("GMP") and the construction schedule for the construction phase of the project.
● Unlike traditional design-bid-build procurement, the CM/GC project delivery method allows for
construction to begin before design is complete (via Early Work Amendments), reducing the
overall project schedule.
5. Schedule
Building design based on the revised comprehensive plan began in May, 2025. The design will
need to navigate a multi-step land use approval process, and multiple building permits; construction
is planned to begin in the summer of 2026.
Students and staff will remain on site during construction, and will be kept separate and safe from
the impact of that construction.
An Early Field Phase of construction is planned to start in the summer of 2026, with Site
Preparation to begin in the Fall of 2026 and Building Construction to begin in the Winter of 2026/27.
Construction is planned to be complete by the summer of 2029, with move-in of students & staff into
the new building in the Fall of 2029. Abatement & Demolition of the existing building will start in the
Fall of 2029, followed by Site Construction of the track & field which will be completed by the fall of
2030.
6. Budget
Following the completion of the cost reduction study in April 2025, the overall project budget for
the Jefferson High School Modernization project is currently set at $466,007,500. This budget
breaks down as $372,075,017 for hard construction costs, $46,901,160 for professional services,
$24,924,383 for owner costs, and $22,106,940 for contingency. Please see attached budget for
estimated allocations.
7. Communication / Coordination
The team provides regular updates on project status via e-builder project status updates, regular
Steering Committee meetings to District leadership and quarterly updates to the Bond Accountability
Committee as needed. The project team is also holding regular meetings with District stakeholders
during design to keep them up to date on project scope, design standard deviations, and other issues.
3 | Page
PROJECT TEAM MANAGEMENT PLAN
rev. 5/7/26
Community engagement has been a central part of the Jefferson Modernization Project since day
one. Funded by the 2020 Bond, the project has prioritized meaningful input from students, families,
staff, and local stakeholders throughout the planning and design process, including the following -
● More than 4,500 comments gathered through surveys, workshops, open houses, and
more
● Major engagement events included:
○ 5 Conceptual Master Planning Committee (CMPC) meetings
○ 7 Comprehensive Planning Committee (CPC) meetings
○ 7 Town Halls
○ 6 Design Advisory Group (DAG) meetings
○ 5 Community Design Workshops (CDW)
○ 5 Community Information Sessions (CIS)
○ 2 Design Justice Workshops
● Staff engagement: Attendance at JHS Staff meetings, school department specific
meetings and meetings with district leadership staff
● Student and family outreach: Classroom visits, the Demo Design Club, PTSA
meetings, and community tabling at events like Back to School Night, Good in the
Hood and Juneteenth
● Ongoing communication: Meeting materials and summaries are available to the public
to ensure transparency and continued access.
8. Governance/Reporting
Project decisions that are within the authority of the project team are made at the discretion of
the lead project manager in consultation with members of the project team, other RISE members,
Facilities Management, school personnel, and third party design consultants as needed. For decisions
beyond the authority of the project team, decisions are forwarded to the appropriate party with any
background information needed to assist in making the decision. Project decisions and actions will be
reported out to the appropriate parties as discussed in the project communication plan, through
meetings, emails, or e-Builder correspondence.
9. Procurement Methodologies
To procure architectural design services for the Jefferson High School Modernization project, the
project team utilized a formal RFP process in conjunction with PPS Purchasing and Contracting to
solicit proposals from interested parties. The RFP’s qualifications-based criteria prioritized certified
business participation and workforce diversity.
To procure construction services for the JHS project, the project team determined that the
Construction Manager/General Contractor (CM/GC) method was the most appropriate for this type of
large, complex project. Having been granted an exemption from the traditional Design-Bid-Build
low-bid procurement process, the project team issued a CM/GC RFP, in which selection was based on
evaluation of factors relating to experience, expertise, project approach, certified business
participation and workforce diversity, rather than lowest bid
Contracts for all other miscellaneous services, including, but not limited to arborist tree survey
report, land survey, geotechnical investigation/report, hazardous material survey, and building
commissioning services, were procured through one of two approaches. For smaller scopes of
4 | Page
PROJECT TEAM MANAGEMENT PLAN
rev. 5/7/26
service, the project team has directly appointed small, certified firms where possible to complete this
important project work. For larger scopes of service, the project team is utilizing the formal RFP
process to select qualified firms that could complete a number of tasks over the life of the project.
10.Certified Business Recruitment Plan
PPS Purchasing and Contracting has an aspirational goal of 18% or more of project contracts by
cost be awarded to certified firms. To achieve or surpass this goal on the Jefferson High School
Modernization project, the project team is utilizing multiple strategies to attract, contract, and
execute work with certified firms. For the RFP for architectural services the project team included
categories to both proposal and interview panels requesting information and providing scoring on
potential firms certified business strategies and internal workforce diversity. On the CM/GC RFP the
project team included evaluation criteria in the RFP to help ensure the selection of a prime contractor
with a strong commitment and demonstrated success in using Certified minority firms as well as a
substantive plan of outreach to, partnership with, and inclusion of Certified subcontractors.
On smaller procurements for goods, services, and other professional services, the project team is
soliciting proposals from multiple companies, especially recruiting from certified firms whenever
possible. The project team is also attending certified business trade gatherings such as those put on
by OAME wherever possible to recruit potential certified firms who have not previously worked with
the District.
11. Challenges/Opportunities
The challenges of the project include a tight, phased design & construction schedule, a
constrained site, and occupancy of an active construction site by students & teachers.
Each of these challenges offer opportunities, including careful coordination among the
owner-architect-contractor team & stakeholders in order to meet the ultimate completion dates,
careful planning from a facility and programmatic standpoint in order to minimize impact on students
& teachers, and a strategic approach to pre-construction planning & investigations.
12.Appendices (embedded links)
Attachment 1: Draft Schedule
Attachment 2: Draft Budget
Attachment 3: Team RACI Matrix