Board of Education
To: Board of Education
From: Dr. Kimberlee Armstrong, Superintendent
Joanna Evenson, Senior Director, Real Estate, Infrastructure & School Enhancements
Date: October 20, 2026
Draft Findings in Support of Alternative Contracting Method and Use of Request for Proposals
Solicitation for 2027 Seismic Construction Projects- specifically Beverly Cleary Fernwood, Richmond,
Capitol Hill, Ainsworth, & Kelly
REQUEST: Staff requests that the Board of Education (“Board”), acting as the Local Contract Review
Authority for the Portland Public School District (“District”), grant an exemption from the traditional
Design-Bid-Build low-bid procurement process and approve the use of an Alternative Contracting
Method for the seismic construction upgrades at the following sites, scheduled for summer 2027 start:
Beverly Cleary Fernwood, Richmond, Capitol Hill, Ainsworth, and Kelly (the “Projects”). Specifically, staff
seeks to use a Request for Proposal (RFP) solicitation process. Staff will issue an RFP that will include
both qualifications criteria and a lump sum cost proposal to select the contractor (“Proposer”) for the
Project.
PROJECT DESCRIPTION: The May 2025 Bond, as approved by voters, prioritizes seismic improvements at
8 to 10 schools that pose the greatest risk in a significant seismic event. On May 6, 2025, the Board
passed Resolution 7109 - Urgent Need for Seismic Retrofitting of High-Risk School Buildings, and
Resolution 7110 - Resolution to Affirm the Board of Education’s Commitment to Track and Report
Findings, Public Engagement and Recommendation of Seismic Upgrades through the School Facilities
Improvement and Operations Committee.
On September 9, 2025, the Office of School Modernization (OSM) presented three options to the Board
of Education for moving forward with select seismic rehabilitation utilizing one of three criteria set forth
below:
Option A would be complete seismic retrofits to bring several buildings up to current Oregon Structural
Specialty Code and Fire and Life Safety Code (OSSC) standards. This option allows the district to
maximize construction efficiencies, ensures seismic compliance for the entire campus, and allows the
district to take advantage of the Seismic Retrofit Grant Program offered by the state of Oregon. This is
the option currently chosen for this project.
Page 1
Option B would designate several buildings to receive partial rehabilitation. These partial retrofits
achieve the greatest district-wide risk reduction by addressing the most dangerous conditions first.
There are no SRGP grants available for partial retrofits.
Option C uses a hybrid of options A & B, which will combine full seismic rehabilitations at a few schools
and partial seismic rehabilitations at more schools.
RISE has implemented Option C, completing partial seismic upgrades at Ainsworth & Kelly, partial seismic
upgrades combined with partial roof replacements at Richmond & Capitol Hill; each of these are
separate construction packages. A full seismic upgrade will occur at Beverly Cleary Fernwood. The
seismic upgrade at Ainsworth has been awarded a grant of $1.5M from the Oregon Seismic
Rehabilitation Grant Program.
This work at each school may include some or all the following work: structural improvements to bring
the building or more hazardous parts of the building to risk category III standards, roof replacements ,
hazardous material abatement, mechanical/electrical/plumbing upgrades, information technology
installations, new interior partitions, architectural finishes, and/or landscaping.
The construction cost varies by site; Beverly Cleary Fernwood has a construction rough order of
magnitude (ROM) of $18.7M, Richmond ROM (including partial roof replacement) is $6.5M, Capitol Hill
ROM (including partial roof replacement) is $12.4M, Ainsworth ROM is $2.3M, and Kelly ROM is $1.6.
Funding for all seismic work will come from the 2025 Bond funds set aside by Board Resolutions 7109 &
7110; the roof replacements at Richmond and Capitol Hill will be funded by the 2017 Bond. Each of
these project’s schedules has targeted June 2027 for the start of project-related construction.
These projects will address many challenges and require careful planning and coordination during the
design and construction phases to complete these scopes effectively and efficiently. Detailed budget
and schedule controls are essential to the project’s success. It will be important to utilize a construction
firm with the following specific traits:
• Company and staff skills and experience with projects of this size, scope and complexity –
relevant project experience lowers the risk of cost and schedule overruns due to better
understanding of project needs, availability of appropriate company resources for size and
complexity;
• Experience with phasing, staging, and construction means and methods that are sensitive to
possibly-occupied facilities and surrounding residential neighborhoods – construction work will
be occurring within tight urban constraints and may be in occupied facilities;
• An exemplary history of on-time delivery with an aggressive timeline – the facilities to be
developed by the project must be delivered in a timely manner due to program and enrollment
needs;
• Ability and commitment to in-depth engagement of the local subcontracting community in
support of the District’s Equity in Public Purchasing and Contracting programs;
• Flexibility and creativity in addressing unique opportunities and unforeseen conditions –
existing infrastructure often provides unexpected challenges with a short timeline for resolution;
and
• An understanding of the importance of a collaborative and tightly integrated project team.
Page 2
ALTERNATIVE CONTRACTING METHOD: The conventional design-bid-build contracting methodology
(DBB) that is considered competitive bidding under Oregon Revised Statute (ORS) 279C, and therefore
represents the basis of public improvement contracting in the State of Oregon, would expose the District
to a significant amount of risk based on the parameters of this project. DBB, which only considers the
lowest priced bid that conforms to the bidding requirements, does not allow the District to consider any
of the above qualities when selecting the most appropriate contractor. An alternative contracting
process is authorized for procurement of construction services under ORS 279C.335, provided that the
Board of Education, acting as the local contract review board, approves an exemption from competitive
bidding. To appropriately manage the critical needs within this project, PPS staff recommend using an
open and competitive Request for Proposals methodology. Under this Request for Proposals contracting
method:
• Contractors will be solicited with a competitive Request for Proposals (RFP) process that utilizes
both qualitative and cost criteria for selecting a qualified contractor.
• Qualitative criteria may include prior successful experience with similar project issues; adequacy
of equipment and labor; sources of supply; availability of key personnel; financial capacity; past
performance; safety records; project understanding and approach; proposed methods of
construction; proposed milestone dates; references; commitment to and successful history of
engaging Certified Business subcontractors and a diverse workforce; and other matters that
affect cost, quality, schedule or other District needs.
• Cost criteria will be addressed by submission of a lump sum cost proposal as part of the RFP
response.
• The RFP process will be a publicly noticed, competitive process allowing all interested
contractors to submit proposals. A contractor will be selected based on the scored evaluation of
their qualifications and cost proposal.
The Request for Proposals utilizing both qualification criteria and a lump sum cost proposal has been
successfully used by the District on prior large, complex projects, including the bond-funded Kellogg
Middle School replacement project and the Harrison Park Middle School Conversion project.
FINDINGS: Following are the factors for consideration under ORS 279C.335 (2), in bold, followed by
staff’s findings.
“(a) The exemption is unlikely to encourage favoritism in awarding public improvement contracts
or substantially diminish competition for public improvement contracts.”
The requested exemption will not encourage favoritism or substantially diminish competition.
The District will utilize a competitive Request for Proposal (“RFP”) process. That procurement is
formally advertised with public notice and disclosure of the planned Alternative Contracting
Method. Full competition will be encouraged, and this competitive process will include
significant staff outreach to and solicitation of certified minority owned, women owned, service
& disabled veteran owned, and emerging small business contractors (“Certified Businesses”) in
Page 3
accordance with the District’s values and policies. The general contracting market is familiar with
the RFP process and accepts it as a standard, and often preferred, delivery method. The award
will be based upon review and scoring of submitted proposals through identified selection
criteria, by a diverse District review committee representing a broad range of experience and
qualifications. The lump sum cost proposal component will encourage the same vigorous
competition of a design-bid-build procurement methodology and provide opportunity for all
interested contractors to participate in bidding for the project, while recognizing that quality is a
critical component of cost.
"(b) Awarding a public improvement contract under the exemption will likely result in substantial
cost savings and other substantial benefits to the contracting agency or the state agency that seeks
the exemption or, if the contract is for a public improvement described in ORS 279A.050
(3)(b), to the contracting agency or the public.”
Through the use of the RFP process to ensure successful Proposers are experienced with the
scope, scale and unique qualities of the Project, the District limits its risk of changes to the final
contract amount due to incomplete or inaccurate bid estimates.
“In approving a finding under this paragraph, the Director of the Oregon Department of
Administrative Services, the Director of Transportation or the local contract review board shall
consider the type, cost and amount of the contract and, to the extent applicable to the particular
public improvement contract or class of public improvement contracts, the following:”
“(A) How many persons are available to bid;”
Based on previous District RFP construction procurements, it is reasonable to anticipate between
four to six firms will propose on each of these seismic projects. PPS staff and partners have
performed outreach to local general contractors, who have expressed a preference for a
qualifications-based approach to bidding these types of projects.
"(B) The construction budget and the projected operating costs for the completed public
improvements;”
The estimated construction cost is set forth above in the project description. The District has not
yet conducted a detailed analysis of the operating costs, but operating costs are not expected to
change significantly in either direction once construction is complete. Given the invasive nature
and unpredictability of the proposed large-scale infrastructure improvements, having an
experienced contractor on the Project will help minimize unexpected increases in construction
costs.
"(C) Public benefits that may result from granting the exemption;”
Page 4
An RFP process allows the District to review the resumes and references of the Proposer’s
project team, ensuring the selected Proposers have the necessary experience, expertise, and
stakeholder-centric approach to address the Project’s unique needs. In a traditional
design-bid-build procurement, the District awards to the lowest responsible bidder regardless of
the above factors. This process would increase risk for the Project, the District, and the
community by potentially awarding the bid to a contractor who does not have the qualifications,
knowledge or experience to successfully complete the Project.
"(D) Whether value engineering techniques may decrease the cost of the public
improvement;”
Value engineering is a routine practice in public improvement projects regardless of procurement
method. The selection of an experienced contractor through the RFP process will provide
additional opportunities to decrease costs with the contractor’s knowledgeable implementation
of material submittals, phasing plans, labor allocation and other means and methods.
"(E) The cost and availability of specialized expertise that is necessary for the public
improvement;”
The RFP process allows for review of contractor expertise not afforded in traditional
procurement. These seismic upgrade projects will require extensive renovations and invasive
infrastructure improvements on a tight schedule, including periods where the site may be
occupied. Through the RFP process, a contractor can be selected that demonstrates expertise in
managing, scheduling and performing successfully in these types of conditions.
"(F) Any likely increases in public safety;”
The existing sites are located in established residential areas and may be partially occupied for
periods of the construction. The use of the RFP process allows the District to request a
contractor’s safety protocols and history as part of the selection criteria. Selection of a
contractor with strong protocols and history for the Project will help improve public safety
during demolition, hazardous material abatement, construction in occupied areas, and routing of
pedestrian, bicycle, and vehicle traffic around construction site access.
"(G) Whether granting the exemption may reduce risks to the contracting agency, the state agency
or the public that are related to the public improvement;”
The RFP process will reduce risks to the District and the public through selecting a qualified and
experienced contractor. It will improve scheduling, planning and coordination of the Project,
thereby reducing financial, schedule, and safety risks.
"(H) Whether granting the exemption will affect the sources of funding for the public
improvement;”
Page 5
There will be no impact on the funding of the Project if the exemption is granted.
"(I) Whether granting the exemption will better enable the contracting agency to control the
impact that market conditions may have on the cost of and time necessary to complete the public
improvement;”
The exemption will not change the District’s ability to control cost and schedule impacts of
current market conditions.
"(J) Whether granting the exemption will better enable the contracting agency to address the size
and technical complexity of the public improvement;”
Granting the exemption will help successful seismic (full or partial) rehabilitations at five schools.
Due to the technical complexity of the Project, careful coordination, staging and scheduling will
be essential to project success. The RFP process will allow the District to choose contractors who
demonstrate successful performance history with these types of project challenges and better
enable the District to address the technical complexity.
"(K) Whether the public improvements involve new construction or renovate or remodel an
existing structure;”
The Project will involve renovation of an existing structure. Procuring a contractor with
experience in complex renovations of occupied structures involving facility infrastructure is
critical.
"(L) Whether the public improvements will be occupied or unoccupied during construction;”
The full seismic rehabilitation at Beverly Cleary Fernwood will require the site to be unoccupied
during the 12-14 months construction is happening. The other four sites may be partially
occupied by staff and/or students; however, phasing plans have yet to be finalized for all four
sites. Using the RFP process allows the district to choose a contractor who has experience with
complex phasing and scheduling.
"(M) Whether the public improvements will require a single phase of construction work or
multiple phases of construction work to address specific project conditions;”
The seismic rehabilitation at Beverly Cleary Fernwood will be completed in one phase while
students attend classes at a swing site. The partial seismic improvements at Ainsworth, Kelly and
Richmond are anticipated to be completed in one summer; while the partial seismic
improvements at Capitol are anticipated to be completed in two summers. The exemption will
allow the District to evaluate the contractor’s qualifications in successfully delivering projects
with complex and/or compressed schedules, and/or multiple phases.
Page 6
"(N) Whether the contracting agency or state agency has, or has retained under contract, and will
use contracting agency or state agency personnel, consultants and legal counsel that have
necessary expertise and substantial experience in alternative contracting methods to assist in
developing the alternative contracting method that the contracting agency or state agency will use
to award the public improvement contract and to help negotiate, administer and enforce the
terms of the public improvement contract;”
RISE and PPS Purchasing & Contracting department have department staff that have the
necessary expertise with the proposed alternative contracting method to develop and effectively
utilize the RFP method for these construction packages at five schools in need of seismic
rehabilitation.
CONCLUSION: For the reasons stated above, the draft findings support an exemption from competitive
bidding under ORS 279C.335 to utilize the proposed RFP contracting method for the 2027 Seismic
Construction Projects- specifically Beverly Cleary Fernwood, Richmond, Capitol Hill, Ainsworth, & Kelly.